Jajmau Ganga Bridge Repair in Kanpur Set to Wrap Up by December 13, Commuters Face a Few More Weeks of Jams
The Jajmau Ganga Bridge Repair on the Kanpur-Lucknow highway has entered its final stretch, and the National Highways Authority of India (NHAI) is now working towards finishing the job by December 13. For the thousands of people who cross the Ganga between Kanpur and Shuklaganj every day, that means roughly 19 more days of slow traffic on a route that has been choked for more than 70 days.
The old bridge at Jajmau was closed to heavy vehicles on September 13 for a repair programme planned to last about three months. Since then, the burden of the busy highway has fallen largely on the newer Ganga bridge next to it, and long queues have become a daily sight at the Kanpur end near Jajmau and Ramadevi as well as on the Unnao side around Shuklaganj.
What is being fixed on the old bridge
The bridge had developed serious wear in its bearings, the components that let the deck sit and move safely on its piers. According to NHAI, 68 bearings on the ageing structure needed replacement, and by late October work on 42 of them had been completed. Alongside the bearings, the contractor is repairing the expansion joints and relaying the asphalt on the deck.
The new road surface on the half lane that carries traffic from Lucknow towards Kanpur is now ready, and officials say that has already brought noticeable relief. The remaining work is concentrated on the other half of the carriageway, towards Lucknow. To limit disruption, the agency is trying to complete any task that affects moving traffic before the evening rush builds up.
NHAI’s project manager on the site has said the target is to finish the Jajmau Ganga Bridge Repair by December 13. Earlier in the work, officials had hoped the bridge might be ready a few weeks ahead of that date, but the December deadline remains the working goal.
Saraiyan overbridge eases some pressure
One development that has helped Kanpur commuters is the opening of the railway overbridge at the Saraiyan crossing on the road from Marhala Chauraha towards the Ganga Barrage. The bridge was thrown open to traffic on November 4, giving light vehicles an alternative route towards the barrage side and reducing pressure on the Jajmau crossing.
Heavy vehicles, meanwhile, continue to be diverted through Unnao and Fatehpur via the Buxar Ganga bridge. The detour adds considerable extra distance for goods vehicles, and travellers between Kanpur and Lucknow have had to plan for longer journeys since the closure.
Breakdowns make bad days worse
With the new bridge carrying most of the load, even a single breakdown can paralyse the highway. On Sunday evening, a dumper loaded with sand stalled in the middle of the new Ganga bridge at Jajmau because of a battery and technical fault. Within minutes, a queue of nearly three kilometres built up towards Ramadevi on the Lucknow-bound side, and many motorists were stuck for about an hour. Traffic police had to bring in a crane to clear the vehicle before movement returned to normal.
For daily commuters from Shuklaganj, many of whom work or study in Kanpur, the episode was a reminder of how little spare capacity the crossing has until the old bridge reopens.
Why the Jajmau crossing matters
The Jajmau bridges are among the most important links between Kanpur and Lucknow and carry a large share of the traffic between the two cities, including goods vehicles heading to eastern Uttar Pradesh. The leather and industrial belt in Jajmau and the fast-growing residential areas of Shuklaganj on the Unnao side depend heavily on this crossing.
Once the Jajmau Ganga Bridge Repair is complete, both bridges are expected to carry traffic again, which should ease the bottleneck that has troubled Kanpur since mid-September. Until then, motorists can expect slow movement at peak hours, and the Ganga Barrage route via the Saraiyan overbridge remains an option for lighter vehicles.